BUILDING UPDATE-MAY 2020

We are invited to attend the PCG zoom meeting today. There is still some restriction on work under Level 3, but we are very excited to see moving on.

LEP reported the progress, site shed and fences set up, site stripped of topsoil down to good ground, site survey completed.

For the next two weeks, LEP will place and compact fill to underside of rib raft pods except where block wall foundations are, underslab services, commence foundation construction.

Brilliant!!